Lunenburg · The RegionMunicipal Building Design CommitteeMonday, Aug. 31 · the meeting ran 90 minutes

Building Design Committee explores feasibility study for senior housing at T.C. Passos

Committee members and a guest speaker discussed repurposing the former elementary school for senior housing and a community center. to meet state housing thresholds.

at its Aug. 31 meeting
at its Aug. 31 meeting Video still: Lunenburg on YouTube

Esta noticia todavía se está traduciendo; aquí está en inglés.

Listen · Read aloud; the words light up as you listen

LUNENBURG — The Municipal Building Design Committee discussed a possible feasibility study for senior housing at T.C. Passos and agreed to gather cost estimates; its only recorded vote was that the current building's square footage is insufficient for all town functions.

How they votedas heard in the recording
  • Motion stating that the current building square footage is insufficient for all town functions — Unanimous (Aye) 56:22
  • Motion to adjourn — Unanimous (Aye) 89:42
The meeting in a minuteVideo brief · 0:43Watch More briefs →

Senior Housing Proposal

Mr. Wallace, a guest who previously worked in Westminster, presented a plan based on his experience there, where a 50-unit affordable senior housing project was built on town-controlled land behind the senior center 2:21. Gray noted that the town is currently at 8.21% of the 10% threshold for units deemed affordable by the state under MGL Chapter 40B, leaving it approximately 85 to 89 units short 7:13.

The committee discussed using the T.C. Passos site for senior housing, a community center, and a town green, aligning with the town master plan which identifies the location as ideal for these uses 27:14. Wallace estimated that a feasibility study would cost between $50,000 and $75,000.

Town Hall Renovation

The committee also addressed the renovation of the current Town Hall, noting that the building's current square footage is insufficient for all town functions 56:12. Members discussed the need for an elevator to eliminate split floors and ensure accessibility, as well as the potential to move the Veterans Affairs and Facilities departments to other locations to free up space 42:02.

A previous renovation estimate for the Town Meeting House included $4.5 million in soft costs, one member said he thought the annex inflated that figure. The committee agreed to draft a document outlining square footage requirements and assumptions to present to the Select Board and Town Manager 77:23.

T.C. Passos Operations

The committee noted that the primary boiler at T.C. Passos failed its inspection, and the second boiler has a control device described as 'Windows XP' 77:53. The town has funds to pay the building's utilities through June 30, 2027.

Replacing the defective leaky steam safety valve at T.C. Passos is estimated to cost $5,000 or less 79:42. For comparison, boiler replacement at St. Bernard's Elementary School by Boylstein Heater out of Gardner cost $300,000, and a new roof for the multipurpose room there cost $80,000 79:10.

One member suggested the food pantry and teen club put money toward repairing the boiler valve, with the Select Board deciding to keep the building open during the winter 79:32. The MassWorks infrastructure grant application window opens next spring, which could potentially fund the feasibility study 32:29.

What's next
  • The next Building Design Committee meeting is scheduled for the 21st 88:53. The committee will work on drafting the square footage document and seeking ballpark estimates for the T.C. Passos feasibility study.
A name wrong in this story? Tell us
A figure wrong in this story? Tell us
Who is in this picture?help name the people in it

Know someone in the picture? Sign in to tell the editors — no password, a link by email.

More from the

Municipal Building Design Committee

All coverage

Every meeting: the written story, and a one-minute video brief.

Comments

0 so far
No comments yet. Be the first.

Sign up to comment

Your name shows with your comments; your email never does. We send one email — tap it and you are back here, signed in, ready to comment. No password.

Comments from signed-up readers appear at once. No links. Off-topic, spam and abusive comments are taken down. Already signed up? Sign in.