Planning Board Approves Modified Site Plan for Spring Street Solar Installation
Cet article est en cours de traduction ; le voici en anglais.
Rodney Galton of ECOS Energy LLC appeared before the Planning Board at their meeting on Tuesday, August 2 to request approval of a site plan modification for the proposed solar array at 875 Spring Street. This project has been pending for some two years, with ECOS Energy first appearing before the Planning Board in August, 2020 (see "ECOS Energy Plans Solar Array on Spring Street" in the August 20-27 2020 edition of The Winchendon Courier ). The initial hearing for the site approval was continued through multiple Planning Board meetings from August through November 2020.
Mr. Galton opened his presentation by explaining, "In late 2020, this project was approved and due to several factors, part of it was COVID, and supply chain issues, the modules that we had originally ordered and designed the project for are no longer available. So we have been searching for modules that are available to us. We finally found some, so we redesigned the project based on those modules we were able to procure. So based on the larger more efficient modules, we were able to reduce the footprint quite a bit." He pointed out two arrays on the original plan which have been completely eliminated, reducing the amount of footprint by about seven acres. In addition, the distance from the array to the abutter on the east, or Ashburnham, side has been increased from 148 feet to 184 feet.
The original plan included a seven-foot chainlink fence around the perimeter. ECOS Energy was now proposing to use a type of fencing they are using in other installations. "It's a wood post and a fabric known as fixed knot. It actually looks much more agricultural and it's much less industrial looking. So therefore it's a lot less offensive to the eye. And we've been using that in Vermont, in Vermont we're required to use it, but we've started to use it in all of our projects. Because people just tend to prefer that over the industrial looking chainlink fence," Mr. Galton said. Regulations require the fence to be at least seven feet high.
The third change involves eliminating concrete pads around the site for equipment, and instead constructing a garage near the road (Route 12) where equipment will be protected from the weather. "We find that here in New England some of the equipment doesn't do well during the transition periods, spring and fall where you have that freeze-thaw cycle. A lot of the equipment, especially the gaskets, don't react well to that," he explained. The garage will be by the entrance gate and close to the utility pole.
Planning Board member Burt Gould brought up the concerns raised by the abutter on the east, saying that resident should be notified of changes to the site plan. "I've had several conversations with that abutter, I know their concerns," Mr. Galton responded. "They don't believe the property line shown on the survey is what it is. But we've had that verified twice now and we are increasing the distance from the array to that residence...we're adding over 35 feet of distance between that residence and the array itself."
He went on, "we have not adjusted the buffer zone only because of where we're putting the fence. I have spoken with that abutter, and they...think that the vegetation is dense enough that they don't feel anything needs to be added. And I have to get that in writing. I know that that's part of the conditions, but they did not feel that any additional vegetation would be needed."
The Planning Board members in attendance voted to approve the modified site plan.
Minutes of August 18, 2020 Planning Board Meeting with beginning of ECOS Energy hearing (PDF)
Minutes of October 20, 2020 Planning Board Meeting with continuation of hearing (PDF)
Minutes of November 17, 2020 Planning Board Meeting with continuation/conclusion of hearing (PDF)
Complete packet for modification of site plan application, 7/13/2022 (PDF)

Comments