Ground preparation savings
$500,000Ken Wante will hold a further meeting with the Department of Public Works regarding ground preparation, where DPW estimated best-case savings of about $500,000. — Ken Wante
Your town's news, meetings and weather come first. Everything else is still there.
We remember it on this phone. Signed in? It is saved to your account too.
What every board is dealing with, followed from meeting to meeting — open until it is decided.
Ken Wante will hold a further meeting with the Department of Public Works regarding ground preparation, where DPW estimated best-case savings of about $500,000. — Ken Wante
Chief Smith was assigned to contact the original architect to identify further cost items and clarify the need for a third paid pre-design or RFQ expense. — Chief Smith
Lauren Raps will speak with state representatives to determine if any external funding is available for the new station. — Lauren Raps
The storyFire Chief Tom Smith presented a summary of physical needs including bunk rooms and garages, with a prioritized list due at the next meeting. — Tom Smith
The storyKen Wante presented plans and estimated costs for a Triumph Modular building, with a follow-up planned to break down costs between living quarters and garages. — Ken Wante
Chief Smith will provide a prioritized list of needs at the next session. — Tom Smith
Chief Smith identified the need for space to house all apparatus inside the building. — Tom Smith
The committee reviewed a plan for six bunk rooms with three shower/bathrooms and a dedicated decontamination space. — Tom Smith
Kevin Sutton reported that he contacted Titan Steel for a bid on a metal building and is currently waiting for their response. — Kevin Sutton
Erika Eitland was assigned to take over the minutes for the committee. — Erika Eitland
The committee agreed that Brian Croner will serve as an advisor to the board. — Brian Croner
The board agreed to formalize a multi-part fundraising effort including engraved bricks and a memorial wall to supplement town funding. — Ken Wante
The committee voted to target a spring or June town vote for a new modular fire station after the cost estimate dropped to $11 million. — Kevin Sutton, Ken Wante
The committee unanimously elected M. Ward as vice chair. — M. Ward, D. Coulter, K. Sutton