Fire Station Redesign Proposal and Plans Moving Forward
Esta notícia ainda está sendo traduzida; aqui está em inglês.
Redesign plans for the Town of Winchendon Fire Station continue to move forward towards a Fall 2022 Special Town Meeting proposal to voters, with a downsized proposal reducing the total project cost, as the current facility continues to fall short of meeting codes, department needs, and requirements.
At the Fall Special Town Meeting held on October 28, 2020 under the administration of former Town Manager Keith Hickey, a large proposed expansion of the station with a new building connected to the existing fire department was rejected by voters. The Finance Committee recommended against the estimated $12 million project proposal, explaining that the expansion project had not gone through what it considered to be the proper channels and procedures for adequate discussion among various town committees, and had bypassed the Capital Planning Committee.
During that Town Meeting, residents also voted down an additional override debt exclusion request of $853,000 for the necessary architectural design and all associated documents of the project regarding potential construction. Based on the discussions and "No" vote by Town Meeting, voters then passed over the request to approve $200,000 to be take from free cash to fund a project OPM (Owners' Project Manager).
The Finance Committee Chair, Tom Kane, said the FinCom felt there had not been enough discussion regarding the project, especially regarding costs, and did not understand the need to rush it. Kane added that while the committee understood something needed to be done, more people needed to be afforded the opportunity to ask questions and be part of the process. Now, over fifteen months later and after much planning, that time will soon come. Talks and discussion, Q&A sessions, and a future proposal on the table for voters, if all goes according to plan, will be taking place for the Fall, 2022 Special Town Meeting (exact date to be confirmed by the Board of Selectmen).
On Wednesday, January 5, Fire Chief Thomas Smith verified to the Courier that there will be announcements soon to come regarding new proposed projected redesign plans, project scope, and potential cost, as well as proposed cost savings verses the original project. Smith said, "We are working diligently with the Town Manager to bring the future proposal to the town. We will be holding in-person meetings as well as possible zoom online meetings if needed. We are working on slide shows among other information which will be available to help answer residents and voter questions, as well as what aspects of a potential future project have been either downsized or eliminated from the original proposal."
At this time a myriad issues currently face the department. Smith confirmed concerns such as not having enough facilities for the proper washing of all clothing and gear, requiring members to bring such items to their personal homes to launder, allowing potential cancer-causing agents to contaminate their private residences. The department garage is at full capacity, not allowing for a fully loaded tanker truck inside during the winter months. The vehicle must be kept empty as it would freeze solid outdoors if filled as needed.
Additionally, there continue to be no separate sleeping or showering facilities for any female employees, as Fire Departments across the nation are seeing employment and membership growth of volunteer, on call, and full time female firefighters. In a 2020 NFPA report based on 2018 data collected, the Nation Fire Prevention Association documented an overview of 29,705 local and municipal fire departments in the nation. Four years ago, in 2018, the NFPA estimated that 93,700, or eight percent, of the 1,115,000 firefighters in the United States were female. More specifically, 15,200 or four percent of career firefighters and 78,500 or 11 percent of volunteer firefighters were women.The current department also fails to meet current ADA compliant regulations as it was constructed nearly five decades ago in the mid-1970s.
When asked about the current upcoming project and proposal on Wednesday, January 5, Town Manager Justin Sultzbach said, "I have been working tirelessly with Chief Smith and a team of architects to reduce the scope and cost of our Fire Station design. The total cost was just over $12,000,000 when it last came before Town Meeting. I am happy to report we have tightened this project up while ensuring the expanded structure stills meets the needs of our Firefighters and the community they serve."
Sultzbach continued, "Rather than put an addition on the existing building which would trigger mandated code updates throughout the building that per square foot can be more costly than new construction, I proposed to the architect a full separate building, which down the road could then be later connected to the existing building with a new addition or feature. This would allow all the existing front line apparatus to be stored in the then new structure next door, that would be significantly smaller than what was proposed, and then allow all the old second line apparatus to be stored in the old fire station."
Elaborating on this, Sultzbach said, "Administrative space, bunk space, and some new bays would go in the new building, and then in the old building could be used for a community meeting room, workout room, the second line apparatus and other purposes. These are things that don't need to be graded as high on modern fire station code but are still perfectly safe for general use, and still experience significant cost savings as you are not fiddling with the existing structure as much."
Requests for funds for the design costs are expected to be made at the Fall, 2022 STM, Sultzbach said. If approved by voters, the design work will take place over the winter, producing a concrete number for project construction costs, as required to put the project out for bid, to be approved by voters at the 2023 Annual Town Meeting in May.
In closing Sultzbach offered, "This early design has been brought before the Capital Planning Committee recently at their December meeting, and will be available for several public input sessions to be held. This is a community project, and it is crucial that we get the community's perspective."