Finance Committee reviews stormwater utility proposal and school track engineering costs ahead of special town meeting
Committee hears details on a proposed $482,000 stormwater budget and a $195,830 engineering request for the high school track, with a public information session scheduled for November 9.

LUNENBURG — The Finance Committee convened on Thursday to review key articles for the special town meeting scheduled for November 17, focusing on a proposed stormwater utility and engineering services for the middle high school track and field facility 1:28. Finance Director Karen Barrett reported that free cash is unlikely to be certified by the meeting date, citing ongoing reconciliation of 54 active bank accounts and 624 active funds 2:17. Barrett noted the town has used the same financial system for 40 years and is working to close out fiscal year 25 before submitting data to the state 7:20.
The meeting in a minuteVideo brief · 0:52Watch
More briefs →Stormwater Utility Proposal
The committee heard a presentation from Bill Bernard, DPW Director, and consultant Jerese Swartz of Weston and Sampson regarding funding mechanisms for stormwater permit compliance 12:47. The town’s stormwater system, valued at over $70 million with 462 outfalls, is estimated to be more than 50 years old 16:06. Swartz outlined a proposed utility budget of approximately $482,000, which includes a dedicated staff engineer and contracted services for catch basin cleaning and street sweeping 23:20.
Under the proposed utility, single-family homes would pay a flat rate not to exceed $100 for the first three years, with a projected fee of $85 per Equivalent Residential Unit (ERU) 21:19. Larger residential and commercial properties would pay based on impervious surface area, with property owners eligible for up to a 50% abatement if they manage their own stormwater 27:00. Bernard stated that street sweeping covers 72 miles of roads in the urbanized area at an estimated cost of $800 per mile 53:26.
Committee members raised concerns about the financial impact on local businesses. One member estimated about $6,000 for Central Mass Garden Center, but a task force member said its fee under the draft data would be $1,497. Another member expressed worry about landscaping businesses with large impervious areas, suggesting the utility could act as a second tax rate 41:43. The task force said it would review the outlier data, and may cap fees at 10% of a property's levy, before sharing the spreadsheet, with a public information session scheduled for November 9 at 7 p.m. at the library 78:12.
School Track and Field Engineering
The committee reviewed a request for $195,830 for professional engineering services to reconstruct the middle high school track and turf field 126:35. The school department reported that the retaining walls may become dangerous, and the bleachers and press box will not be usable for the spring season due to freeze-thaw cycles 129:29. The artificial turf field is approximately 10 years old, reaching the end of its typical lifespan 130:18.
Of the total quote, $61,275 is designated for post-award construction phase services 138:35. Committee members discussed funding sources, noting that if free cash is not certified, the town may need to tap into stabilization funds or other available resources 132:12. The committee emphasized the need for clarity on how the project will be funded and the timeline for completion, with the engineering phase being a prerequisite for seeking grants or state aid 136:41.
Other Financial Matters
The committee also reviewed an amendment to the FY27 omnibus budget, which includes $58,606 in available funds from unexpended state aid and WRAP funds 80:49. Proposed expenditures include a $24,264 account clerk position to assist with filings and reconciliations, as well as MUNIS training subscriptions 83:12. Additionally, the committee discussed a pending bill from Nexam for $5,196.66 from fiscal year 23 97:45.
The committee addressed records retention practices, urging members to ensure documents are properly stored in SharePoint to facilitate public records requests 154:09. The committee also discussed audio quality issues in school committee meetings, with members calling for improvements to live streaming and recording equipment 164:55.
- The cash reconciliation is expected to be finished by the end of next week, which is October 31st or November 1st.
- Fines for noncompliance with stormwater permits range from $5,000 to $50,000 per day.
- Single-family residential properties make up 93% of the parcels in Lunenburg.
- Single-family residential properties make up 59% of the impervious surface area.
- The utility budget includes 4.5% overhead costs.