Gardner school facilities panel votes to send 19 capital improvement projects to Capital Improvement Planning Committee
The Facilities Sub-Committee approved a list of renovations for Gardner Public Schools, noting that final testing for the GMS roof project is scheduled for November 20.
GARDNER — The Gardner Public Schools Facilities Sub-Committee voted on Wednesday to submit a list of 19 capital improvement projects to the Capital Improvement Planning Committee, according to the minutes. The list, presented by Facilities Director Wayne Anderson, includes renovations and repairs for each school building and is described in the minutes as the same list voted on at the previous meeting, minus projects that have been completed or funded. Anderson said the fire alarm system is tested and working properly, but updates must wait until the school is vacated for the summer.
- Approve minutes of previous meetings — So Voted (motion: Mr. Cormier)
- Submit 19 capital improvement items to Capital Improvement Planning Committee — So Voted (motion: Mr. Cormier)
- Set Facilities Committee meetings for the Wednesday prior to School Committee meeting — So Voted (motion: Mr. Cormier)
The committee reviewed the timeline for the GMS Roof project, with Director of Finance & Operations Hawke presented a timeline showing final testing should take place November 20, which should wrap up the project. Anderson reported that issues with a particular sub-contractor have affected the refrigeration units for the cafeteria, though he assured the committee that the problems would be resolved. Anderson, along with the OPM, Engineer, and Contractor, will be “walking the roof” to perform inspections and review deficiencies in workmanship that need to be corrected.
The committee also established a regular meeting schedule for the remainder of the fiscal year, deciding that meetings will be held on the Wednesday prior to the School Committee meeting. The motion to set this schedule was made by Mr. Cormier and seconded by Mr. LaFreniere, and it passed. The meeting was called to order at 5:57 p.m. and adjourned at 6:16 p.m.
- Mr. Anderson, the OPM, Engineer, and Contractor will be “walking the roof” to perform inspections and review deficiencies in workmanship that need to be corrected.
In their words
“walking the roof”
— Mr. Anderson · Projects UpdateWrong name?