Planning Board continues hearing on 599 Spring Street substation upgrade
Public hearing for 61 Railroad Street also continued to October 6

The Winchendon Planning Board met on September 15, 2026, and continued its public hearing for the proposed substation upgrade at 599 Spring Street. The applicant, New England Power Company, represented by attorney Joe Duquette, Per the notice, the applicant seeks site plan approval, a stormwater management permit and a special permit. Attorney Duquette also described earth removal approval and a land disturbance permit.
The meeting in a minuteVideo brief · 0:37Watch
More briefs →The project involves a 29,000 square foot expansion of the existing substation, which has been in operation for over 50 years. The expansion aims to improve the reliability and capacity of electric service in the town. The applicant said the net earth removed is just under 6,000 cubic yards (about 10,800 cut and 4,800 fill).
Durling the meeting, board members discussed various aspects of the project, including traffic management and waivers related to the earth removal regulations and the 140 corridor overlay district.
A board member raised concerns about traffic during construction, noting that Route 12 is highly traveled and people often speed. The applicant's team said it will work with MassDOT and the town on traffic.
Duquette said the condition was certainly well aware of regarding traffic issues and that Duquette was happy again to work with the town, MassDOT, to come up with a reasonable solution. 21:34
The board decided to continue the hearing until October 6th at 6:05 p.m., The applicant said the final peer review copy would be sent to members within the next week. The project is slated for completion in 2029.
In other business, the public hearing for 61 Railroad Street was continued to October 6th at 6:05 p.m.
- The public hearing for 61 Railroad Street was continued from 7-7-26 to October 6th at 6:05.
- The public hearing on September 15, 2026 at 6 p.m. is to consider the request for site plan approval, stormwater management permit, and special permit for property located at 599 Spring Street, Winchendon, Mass. 01475.
- The property at 599 Spring Street is identified as Winchendon, Assessors Map 6, parcels 71 and 72.
- The total amount of cut from the site is just under 6,000 cubic yards.
- There is a total of 10,800 cubic yards of cut with 4,800 cubic yards of fill.
- The project is slated to be completed in 2029.
- The next planning board meeting is scheduled for October 6th at 6:05.
- The peer review report will be sent to the members next week.