Planning Board continues three hearings, appoints designee for Hale Street site visit
The board continued three hearings, including the National Grid substation and School Street contractor bays, to Oct. 20 and set a site visit to a Hale Street property that could hold up to 19 units, though the owner has filed no plan.

Corrected on October 27, 2026. How we correct errors
The Winchendon Planning Board continued all three hearings scheduled for Tuesday, Oct. 6, to Oct. 20 at 6:05 p.m. 13:43.
- Approve minutes from June 16, July 7, and Sept. 15 — Aye 13:09
- Continue hearing for 61 Railroad Street (Munchin Furniture) to Oct. 20 — Aye 15:36
- Continue hearing for National Grid substation to Oct. 20 — Aye 15:36
- Continue hearing for contract to Bates on School Street to Oct. 20 — Aye 16:07
- Appoint designee for Hale Street site visit — Aye 28:33
- Motion to adjourn — Aye 29:43
The meeting in a minuteVideo brief · 0:49Watch
More briefs →Minutes
The board approved the minutes from June 16, July 7, and Sept. 15 13:09. The minutes from Aug. 4 were missing and will be addressed at the next meeting 12:57.
Continued hearings
The hearing for 61 Railroad Street (Munchin Furniture) was continued to Oct. 20 14:36. Crews spent more than a week jetting the pipes and inspecting them by camera, and the report is being reviewed for needed repairs 14:08.
The hearing for the National Grid substation was continued to Oct. 20 15:36. The applicant is still working out peer review comments.
The hearing on the contractor bays on School Street was continued to Oct. 20 16:07. The applicant is still working through peer review issues 16:02.
Hale Street subdivision
The board discussed a Hale Street property of about 39.8 acres 24:35. Under the rules the property could hold up to 19 units, but no application says what the owner intends to build 25:08.
Town regulations require that 50% of the acreage be designated as open space 21:29. The board discussed the possibility of waiving or reducing the 50% open space requirement 24:03.
David Small from Mount Grace Conservation identified areas on the Hale Street lot that might need conservation 18:17. A brook runs through the west end of the Hale Street lot 18:35.
The Hale Street property is located behind the church in Old Center and runs down to Ron Alger's property 22:12. The property is described as heavily treed forest land with wetlands and hilly terrain 21:37.
The board appointed a designee to conduct a site visit for the Hale Street subdivision 28:33. The site visit is tentatively planned for this coming Sunday afternoon, weather permitting.
One member said town meeting could change the regulation's "shall" to "may," so a site visit would not be required before any plan exists 25:57. The board noted that if three or more members attend the site visit, it must be posted as a public meeting 28:17.
The board expressed concern about who would be responsible for maintaining the open space 27:47. A member noted the town had a playground in 2008 and asked who would maintain such open space.
The board noted that the applicant has no plan for what they intend to build on the Hale Street property 24:18. The board planned to discuss the open space designation at a regular meeting after the site visit 19:20.
In their words
“I'd be glad to walk the property out of the yellow seat.”
— Guy Corbosiero · 26:55Wrong name?
A name wrong in this story? Tell us
A figure wrong in this story? Tell us
Know someone in the picture? Sign in to tell the editors — no password, a link by email.