Planning Board backs R3 lot size increase for town meeting, continues battery storage hearing, continues battery storage hearing
Westminster board votes to raise minimum lot size in southern districts and delays final decision on battery energy storage rules to October 13.

WESTMINSTER — The Westminster Planning Board voted to approve a proposed zoning amendment, to go to town meeting, that would increase the minimum lot size in the R3 district, a move intended to preserve rural character without direct cost to the town 4:11 p.m..
- Approval of minutes — Unanimous (Aye) 4:01 p.m.
- Close public hearing on R3 district lot size amendment — Unanimous (Aye) 4:14 p.m.
- Approve R3 district lot size amendment — Unanimous (Aye) 4:14 p.m.
- Continue public hearing on battery energy storage systems bylaw to October 13 — Unanimous (Aye) 4:40 p.m.
The meeting in a minuteVideo brief · 0:39Watch
More briefs →The board voted unanimously to approve the change to Chapter 205-29, which raises the minimum lot size from 86,000 square feet to a new, unspecified figure 4:14 p.m.. The R3 district is located primarily in southern Westminster near the Princeton and Fitchburg borders, including the Whitmanville Farm area 4:11 p.m..
Board members explained that the amendment aims to make it less economical to divide large parcels into many house lots, while still allowing subdivision 4:11 p.m.. The change is described as a way to preserve land and rural character 4:11 p.m..
Battery storage hearing continued
The board continued its public hearing on proposed regulations for battery energy storage systems (BESS) until October 13 at 6 p.m. 4:40 p.m.. The bylaw proposes a tiered system for siting, design, and operation of these systems.
The board agreed to change the terminology for the lowest category of battery storage systems from 'Tier 0' to 'Tier 1' to ensure consistency with other communities 4:17 p.m.. This lowest tier covers systems up to 100 kilowatt hours, which would be allowed by right with a building permit and no planning board review 4:15 p.m..
The bylaw requires larger installations, designated as Tier 2 and Tier 3, to provide fire department training at no cost to the town 4:23 p.m.. This training must cover installed technology, hazards, shutdown procedures, thermal runaway, explosions, and off-gas hazards 4:23 p.m..
Applicants for Tier 2 and Tier 3 installations must supply UL 9540A test reports to the Fire Chief or designee 4:22 p.m.. These installations must also provide and maintain emergency apparatus access acceptable to the fire chief, including compliance with 527 CMR 1 and FPA 1 4:23 p.m..
Gates and fencing doors for these installations must be secured with a Knox box lock determined by the fire chief, and a Knox box document cabinet must be provided by the installer 4:23 p.m..
The board noted that The planning director said a new state law applies to all towns, but the state supplied documents and towns are not required to pass bylaw changes. 4:42 p.m..
Site plan waiver and other updates
The board discussed a site plan waiver request for 2 Hager Park Road, where the owner seeks to convert office space in a two-family home into a third unit 4:01 p.m.. The applicant is scheduled to meet with the Zoning Board of Appeals on September 23 for a special permit hearing 4:01 p.m..
The planning director said he expects the data center amendment to go to the November town meeting.
The board discussed the Adams Street 40B project, noting that the hearing deadline was extended to December 4:49 p.m.. A board member asked whether the project had grown to two buildings and 60-something apartments; the planning director said a two-story version could be done with two buildings. Residents and the zoning board showed little interest in extra units or Bacon Street access, though some were open to hearing about the access.
Diana was introduced as the new land use assistant, replacing Caroline who moved to the health department 4:44 p.m..
- The Westminster Planning Board held a public hearing on September 22, 2026, at 6 p.m. in Room 205, 11 South Street, Westminster Town Hall.
- The applicant for 2 Hager Park Road is scheduled to meet with the Zoning Board of Appeals (ZBA) on September 23, 2026, for a special permit hearing.
- A board member raised concern about the town possibly having to spend something like $100,000 on firefighting equipment.