Zoning Board approves special permit for two-family dwelling on Cummings Road
Permit for contractors' garages on School Street also approved

Cummings Road Special Permit Approved
The Winchendon Zoning Board of Appeals approved a special permit for a two-family dwelling at 10 Cummings Road during their meeting on August 19, 2026. The property, which is on a 2.12-acre lot with 410 feet of frontage, will be converted from a single-family home into two units. One unit will be rented to a local family while the other will be occupied by the owner's son 36:00.
The meeting in a minuteVideo brief · 0:36Watch
More briefs →The permit approval includes conditions such as modifying the existing plans to reflect two bedrooms instead of three on the first floor 26:08. The revised plans must be submitted along with a narrative explaining the changes before any construction can commence 27:54. Additionally, there will be no driveway allowed at the corner nearest the house 40:15.
The septic system for the property is designed for four bedrooms, which aligns with the planned two bedrooms on each floor 23:40. The existing driveway will remain in use until a new permit is obtained from the Department of Public Works 12:21.
Asbestos Remediation and Construction Timeline
An update was provided regarding asbestos remediation at the Cummings Road property. The remediation plan is to be submitted on Monday to the Department of Environmental Protection and the Department of Labor Standards and is expected to take four to five days 21:00. Once completed, construction on the first floor is anticipated to begin within a week, with hopes to complete it by early October 22:13.
A resident at the podium said a resident wanted to tell the board an update on the asbestos remediation contracted with a remediation company out of Westminster. 20:44
School Street Contractors' Garages Approved
The board also approved a special permit for Elaine (Alain) Sitework, Inc. to construct three 7,500 square foot contractors' garages at Zero School Street. The property is currently undeveloped and located in a C2 neighborhood commercial and R80 rural residential development district 44:14.
Justin LeClair from McCarty Engineering presented the plan, which includes three buildings centered on the site with access from School Street 46:24. The project will include stormwater management and will be serviced by wells and septic systems.
The approval follows a peer review by Tyne Bond and requires further approvals from the Planning Board and Conservation Commission. Construction is expected to begin as soon as all necessary permits are secured 50:21.
Electric Substation Upgrade Update
The board discussed an upgrade to an electric substation located at 599 Spring Street. The project, managed by National Grid, involves gravel removal and land disturbance but does not require Zoning Board involvement 5:50. The Planning Board will handle reviews; National Grid's wider power upgrades across Massachusetts are expected to take three to five years.
Nicole (a town official) said National Grid is updating the substation at 599 Spring Street. 5:54
- The hearing for Zero School Street will be held at Town Hall, 109 Front Street, Winchendon, Mass. 01475.
- The hearing for Zero School Street is for a special permit under section 300-5.2 of the Winchendon Zoning Bylaws.
- The Planning Board will meet on September 15th, 2026.
- A 20-day appeal period applies to both special permits approved during this meeting.